Maple Lane
2 unit Development
Floor Area: 184m2
Flexi House provided specialist offsite design and design for manufacture and assembly (DfMA) support to enable this project to be built offsite in collaboration with Frank House and Cameron Builders.
- UNDER CONSTRUCTION -
-
Manufacture: 4 weeks, Sep 2025
Site Assembly: Target of 2 weeks
Completion: 6 months
-
Insulation - R4.0 Wall & R5.0 & R6.6 Roof
R3.0 Quickset Fully Insulated Slab
IBS Rigid Air Barrier
Ducted Mechanical Ventilation
-
GIL-Plans
Engineer: Spencer Homles
Main Contractor: Camberon Builders
Panel Manufacturer: Frank House
DfMA Specialist: Flexi House
1 Sold, 1 Available
Mid-build Open Home - Waikanae
tbc