Maple Lane

2 unit Development

Floor Area: 184m2

Flexi House provided specialist offsite design and design for manufacture and assembly (DfMA) support to enable this project to be built offsite in collaboration with Frank House and Cameron Builders.

- UNDER CONSTRUCTION -

    • Manufacture: 4 weeks, Sep 2025

    • Site Assembly: Target of 2 weeks

    • Completion: 6 months

    • Insulation - R4.0 Wall & R5.0 & R6.6 Roof

    • R3.0 Quickset Fully Insulated Slab

    • IBS Rigid Air Barrier

    • Ducted Mechanical Ventilation

    • GIL-Plans

    • Engineer: Spencer Homles

    • Main Contractor: Camberon Builders

    • Panel Manufacturer: Frank House

    • DfMA Specialist: Flexi House

1 Sold, 1 Available

Mid-build Open Home - Waikanae

tbc